Implementing process of Rural Water Supply & Sanitation projects
under ADB III and its impact on livelihoods
During the presentation the basic principles of the ADB approach
were outlined in detail. The implementing process is basically divided
into six phases (pre-project, social mobilisation, planning and
design, construction, defect rectification and consolidation) spanning
a 21-month period.
PRRA is a key tool throughout, especially for assessing demand and
raising awareness. Village Participatory Planning (VPP) processes
are designed to involve all beneficiaries in decision-making processes
and provide data and information to assist communities in 'self
assessment' and arriving at a decision on the most appropriate supply
option. CBOs are expected to assume full responsibility for the
construction process but are trained in construction management
and quality assurance.
Impact on livelihoods is a central concern under the ADB approach.
This is currently addressed through emphasis on equal opportunities
and ensuring influential and marginalised groups sit together and
discuss their respective problems and needs. The project provides
support to community decision-making processes to help them collect
and analyse their own data. Capacity building and empowerment are
now explicit project objectives. There are a number of requirements
designed to ensure decisions are 'collective' e.g. 75% of the community
must be present at planning meetings and a minimum of 50% must sign
the approved plan. In addition the project monitors women's involvement
e.g. gender composition of CBOs.
Other useful indicators include levels of 'satisfaction' with WATSAN
facilities, and % inclusion of disadvantaged groups e.g. Samurdhi
and female-headed households (see tables). Project data on community
contributions (cash and labour) towards the cost of water supply
and sanitation developments illustrates the high level of demand
for these services.
Community contributions under ADB III
1. Water Supply
Cash Contribution (common facilities) = Rs. 70.1 mill
Cash Investments (private facilities) = Rs. 68.6 mill
Labour Contribution = Rs. 287.1 mill
1. Sanitation
Cash Investments = Rs. 62.4 mill
Labour Contribution = Rs. 41.5 mill
A key challenge identified by the project is reducing the dominance
of elite groups in community expressions of demand for different
technology choices. In some cases discussions have revealed that
elites are willing to pay a greater share of the costs. CBOs are
also encouraged to take the initiative in providing low interest
credit facilities for poorer groups. Data shows that 86.4% of households
pay their tariffs regularly but the vast majority (over 95%) depend
on CBOs rather than banks for credit. Building the capacity of CBOs
to plan, implement and monitor WatSan interventions is a key project
concern. The benefits of enhanced capacity for systematic organisation
and financial management also extend beyond the immediate scheme.
|